Kudankulam reactors have generated over 1.22 lakh million units as of December 2025: Site Director
2026-01-26 - 15:23
Addressing a Republic Day event, he says while the construction of reactors three and four has achieved an overall progress of 83%, the work on reactors five and six has achieved physical progress of 41%, with civil works of all major structures progressing well